Shropshire Council website

This is the website of Shropshire Council

Contact information

E-mail

customer.service@shropshire.gov.uk

Telephone

0345 678 9000

Postal Address

Shropshire Council
Shirehall
Abbey Foregate
Shrewsbury
Shropshire
SY2 6ND

Decision details

Local Plan – Notice of Intention to Commence Plan Making and Scoping Consultation

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

RESOLVED:

 

That Cabinet:

 

1.     Agreed the publication of the Plan-Making Timetable (Appendix 1) and that any subsequent changes to this timetable are delegated to the Interim Service Director for Place Shaping in consultation with the Portfolio Holder for Planning.

2.     Agreed the publication of the Notice of Intention to Commence Plan Making (Appendix 2) in May 2026.

3.     Agreed the Local Plan Project Initiation Document (PID) (Appendix 3), including the governance and decision making arrangements included in Figure 4.1 of the PID, and that any subsequent changes to the PID are delegated to the Interim Service Director for Place Shaping in consultation with the Portfolio Holder for Planning.

4.     Agreed the publication of the Local Plan Scoping Document (Appendix 4), the Draft Community Hierarchy (Appendix 5), the Draft Site Identification and Assessment Methodology (Appendix 6) and the SEA Screening Report (Appendix 7) for public consultation in line with the engagement strategy outlined in the PID, and that any minor changes to these documents ahead of publication are delegated to the Interim Service Director for Place Shaping in consultation with the Portfolio Holder for Planning.

5.     Agreed that delegated responsibility is given to the Interim Service Director for Place Shaping, in consultation with the Portfolio Holder for Planning, for the preparation and consultation of an SEA/SA Scoping document within the Local Plan ‘notification and scoping’ stage.

6.     Noted the Equalities, Social Inclusion and Health Impact Assessment (ESHIA) Stage One Screening Record (Appendix 8)

7.     Agreed, that delegated authority is given to the Interim Service Director for Place Shaping in consultation with the Portfolio Holder for Planning, to agree the completion of Gateway 1 (Self- Assessment) upon the completion of the ‘Scoping’ stage, in order to commence the formal commencement of the plan making in September 2026.

Report author: Eddie West

Publication date: 06/05/2026

Date of decision: 06/05/2026

Decided at meeting: 06/05/2026 - Cabinet

Effective from: 14/05/2026

Accompanying Documents:

 

Print this page

Back to top