Shropshire Council

2021/22 drainage works programme

This information is correct at the time of publishing but could be subject to change either due to circumstances beyond our control, or should other works come in that make it more efficient and less disruptive to reschedule

Closure details

  • Starts: 19 January 2022
  • Ends: 20 March 2022
  • All Shropshire
Area Location Start date End date
Northeast Pear Tree Lane, Whitchurch 07/03/2022 20/03/2022
Northeast Little Soudley Rd, Soudley - Drainage 24hr closure 19/01/2022 28/01/2022
Southeast Astbury Lane, Chelmarsh 07/02/2022 20/02/2022
Southeast Ludlow Rd East Roundabout, Bridgnorth 21/02/2022 06/03/2022
Southeast Lizard Lane Option A - No permit required? 07/02/2022 13/02/2022