Shropshire Council

Little Harlescott Lane, Shrewsbury

This information is correct at the time of publishing but could be subject to change either due to circumstances beyond our control, or should other works come in that make it more efficient and less disruptive to reschedule

Closure details

  • Starts: 4 April 2022
  • Ends: 20 May 2022
  • Central Shropshire

Western Power Distribution (West Midlands)

Outside 69, 71 to Opposite 69

1 joint hole in tarmac footway and 37m trenching in tarmac footway for cable overlay, This has to be done in conjunction with HM5142336716A through to HM5142336716D.

Spoil to be remain on site to be collected bi weekly. Pedestrians to use alternative footway. Traffic lights to be manually controlled between 07:30-09:30 & 16:00-18:30.

Traffic lights will not be required for the duration of works as soon as we can get them off we will and will use give and take.